Analysts feared wider losses, but Silverco secures fresh credit
The Canadian miner secures up to $15 million for the Cusi mine in Mexico and beats market expectations with better-than-feared quarterly results.
BLOCK #9 · block9.net - 02
Silverco secures up to $15 million for Cusi
The prepayment facility funds the Mexican mine through mid-2027. On 16 November 2026, the first shipment of silver concentrate departed after the restart.
BLOCK #9 · block9.net - 03
Quarterly loss narrows to 2 US cents per share
Analysts forecast an average loss of 8 US cents per share. Lower operating costs helped beat expectations and lifted the stock 6 per cent on the Toronto Stock Exchange.
BLOCK #9 · block9.net - 04
Equipment upgrades begin at La Negra
Throughput averaged 1,360 tonnes of ore per day, below the 2,500-tonne capacity. Epiroc delivered a new development drill rig to address site constraints.
BLOCK #9 · block9.net
The Canadian miner secures up to $15 million for the Cusi mine in Mexico and beats market expectations with better-than-feared quarterly results.
Canadian mining company Silverco Mining has secured a financing agreement of up to $15 million, equivalent to roughly €14.2 million, for the restarted Cusi mine in Mexico.
The announcement immediately gave wings to the listed stock on the Toronto Stock Exchange. The share price closed on Thursday 6 per cent higher at 7.30 Canadian dollars, following an earlier intraday climb of 7.1 per cent. This values the firm's total market capitalisation at approximately 408 million Canadian dollars, or around €272 million. These equity gains followed not only the credit facility agreement, but also the publication of its third-quarter results. Silverco posted a net loss of 2 US cents per share, substantially better than the loss of 8 US cents per share that analysts had forecast on average. Lower-than-expected operating costs comfortably offset lower silver grades in the processed ore.
Flexible prepayment facility accelerates Mexican ramp-up
The financing is structured as a prepayment facility tied directly to future sales of concentrate from the Cusi mine, located in the northern Mexican state of Chihuahua. Silverco can draw down the credit at its discretion in tranches. Each individual drawdown carries a maturity of 24 months. This structure avoids immediate equity dilution for existing shareholders and provides the company with the liquidity required to fund the operational scale-up of two underground mines simultaneously through mid-2027.
The facility was granted shortly after a crucial milestone on the ground. On 16 November 2026, the very first shipment of silver concentrate departed the Cusi facility since the complex was restarted. The project had been idle under care and maintenance since September 2023, but was revived as market conditions for precious metals improved. Silverco invested $19.2 million, roughly €18.2 million, into the restart. According to management, this reinvestment remains comfortably within the projected budget—by no means a given in the capital-intensive mining industry.
Thorough overhaul of Cusi and the Mal Paso mill
To ensure commercial viability at Cusi, the company undertook extensive technical upgrades. The project's central processing facility, the Mal Paso mill, was completely refurbished and modernised over recent months. Handover of the plant to the operations team is scheduled for the end of November. At the same time, the mining team is preparing to extract the first ore from the Promontorio stope, which is slated to take place before the end of the current quarter.
On 16 November 2026, the very first shipment of silver concentrate departed the Cusi facility since the complex was restarted.
Meanwhile, underground development in the San Miguel zone continues apace. Silverco is scaling capacity incrementally towards the design throughput of 1,200 tonnes of processed ore per day. The company aims to declare official commercial production at Cusi in the first half of 2027. Once this operational benchmark is achieved, the mine is expected to deliver a steady stream of silver and base metal concentrates to steadily amortise the prepayment debt obligations.
Operational headwinds and fleet renewal at La Negra
However, Cusi represents only half of Silverco's growth strategy. The second pillar is the La Negra complex in the central Mexican state of Querétaro, which the group acquired in May via an all-share takeover of Nuevo Silver. In the third quarter, La Negra operated for the first full quarter under its new owner. The mine processed 125,000 tonnes of ore over the three-month period, producing 161,741 ounces of pure silver. Driven by by-products including copper, lead, and zinc, total production reached 348,578 silver equivalent ounces.
Financially, La Negra generated quarterly revenues of 24.6 million Canadian dollars, translating into an operating mine profit of 3.4 million Canadian dollars. Silverco closed the quarter at the end of September with a cash position of 36.2 million Canadian dollars. Nonetheless, several operational bottlenecks remain to be resolved:
- Processing capacity: The mine operated at an average of 1,360 tonnes of ore per day, representing just over half of its nominal nameplate capacity of 2,500 tonnes per day.
- Ore grade: The silver grade came in at 49 grams per tonne of ore, trailing the estimate of 55 grams per tonne projected by National Bank Capital Markets analyst Alex Terentiew.
- Production costs: Direct operating cash costs stood at $54 per silver equivalent ounce, an increase against the earlier guidance of $50 per ounce.
- Water management: The processing mill faces water management constraints, which forced a cap on raw ore throughput.
To eliminate these bottlenecks, management is investing in new equipment and infrastructure. The first unit of a brand-new underground fleet from manufacturer Epiroc—a development drill rig—has now been delivered on site. Furthermore, Silverco has signed the contractor agreement for the construction of a tailings filtration plant. Stacking dewatered dry tailings will eliminate reliance on conventional tailings dams and resolve water congestion. Commissioning of this facility is scheduled for late June.
In the meantime, exploration drilling around La Negra has yielded encouraging signs for mine life extension. A recent surface drill hole in the Valenciana zone, roughly 650 metres north-west of existing infrastructure, intersected an ore body of 15.65 metres grading an exceptionally high 322 grams of silver per tonne. Underground drilling also indicates that the mineralisation at the Valeria and Brecha deposits extends deeper than previously established.
What these developments mean for Benelux investors
For retail investors in Belgium and the Netherlands, the Silverco Mining case highlights the distinct dynamics of mid-tier resource equities. Investors taking positions in overseas growth stocks via the Toronto Stock Exchange or the US OTC market through European brokers are seeing firsthand how operational execution and financing risk intertwine. Resource companies transitioning from exploration to exploitation are vulnerable to supply-chain inflation and operational setbacks.
At the same time, Silverco's expansion aligns with a broader wave of consolidation and development within Mexico's mining landscape. Sector peer Torex Resources, for example, is currently assessing two major mill expansions at its Morelos complex in Guerrero state, including a $100 million project to expand throughput to 14,500 tonnes per day. Mexico's mining sector therefore remains a key destination for North American mining capital, despite the country's political and permitting complexities.
From our perspective, Silverco has resolved its funding requirement in a relatively elegant manner. Opting for a prepayment facility backed by concentrate deliveries allows management to avoid a heavy equity dilution via a new share issuance, which would have been severely dilutive for shareholders at current market prices. The fact that analysts had priced in a quarterly loss four times as wide shows that the market had taken an overly pessimistic view of the group's cost discipline.
Our take on the stock and the quarters ahead
We believe the true test for the company will only begin in the first half of 2027. Preliminary economic assessments suggest that Cusi and La Negra could jointly yield more than 4 million silver equivalent ounces on an annualised basis. On paper, that figure sounds impressive for a business with a market value of €272 million, but in the mining sector, the gulf between a feasibility study and seamless commercial exploitation is notoriously wide.
The decisive metrics for investors to monitor over coming months will be the timely completion of the tailings filtration plant at La Negra and the stable handover of the Mal Paso mill at Cusi. Unless ore grades at La Negra structurally recover towards the targeted 55 grams of silver per tonne, unit costs will remain stubbornly above $50. With this new $15 million credit facility, Silverco has bought sufficient breathing room to absorb operational teething troubles, but the margin for technical error remains remarkably thin.
- shares
- Bedrijfsresultaten
- Cusi
- La Negra
- mexico
- mining
- Silverco Mining
- Torex Resources
- TSXV
- Silver

Written by
Mathias Peeters
On-chain Analyst · Antwerp (BE)
Expertise
Mathias digs into on-chain data, liquidity, and DeFi protocols. He builds the data models behind Block #9's price and liquidity pages.