Ghent Faces Years-Long Delay for Green Buses as Depot Costs Surge by €30 Million

Block #9

Ghent Faces Years-Long Delay for Green Buses as Depot Costs Surge by €30 Million

Amina El Yazidi
Gent Moet Jaren Langer Wachten Op Groene Bussen Terwijl De Stelplaats Dertig Miljoen Euro Duurder Wordt
6 min
In 4 slidesThe gist of this article, fast
  1. 01

    Ghent faces years-long delay for green buses as depot costs surge by €30 million

    Ghent’s new Wissenhage depot is now projected to cost nearly €200 million, while ageing diesel buses remain stuck on the road due to protracted…

    BLOCK #9 · block9.net
  2. 02

    Depot costs jump to nearly €200 million

    Flemish Mobility Minister Annick De Ridder confirmed the budget rose by €30 million from earlier plans of €170 million.

    BLOCK #9 · block9.net
  3. 03

    Court annuls the environmental permit

    In autumn 2025, the Council for Permit Disputes overturned the permit after activists spent four months in treehouses.

    BLOCK #9 · block9.net
  4. 04

    Over a third of local buses exceed 15 years

    Out of 408 buses operating in East Flanders, 34.1 per cent are at least 15 years old, causing frequent mechanical breakdowns.

    BLOCK #9 · block9.net

Ghent’s new Wissenhage depot is now projected to cost nearly €200 million, while ageing diesel buses remain stuck on the road due to protracted planning disputes.

Anyone walking or cycling across the Gaardeniersbrug in northern Ghent today looks out over an overgrown tram bed leading nowhere. The construction of the new Wissenhage depot in the Bloemekenswijk district is now expected to cost nearly €200 million, according to recent estimates by the Flemish government—a budgetary increase of around €30 million compared with earlier plans of €170 million. The project, on the table for over a decade and intended to become the largest transport depot across Flanders, remains trapped in a web of legal appeals and overturned environmental permits. Flemish Mobility Minister Annick De Ridder and Member of Parliament Bert Maertens confirmed the substantial cost escalation, which is the direct result of years of delays, indexation, and additional studies.

The Wissenhage site is designed to accommodate 120 buses and 40 trams in the long term. Constructing this central infrastructure is an indispensable prerequisite for greening public transport in the Ghent area and preparing it for the future. Without a modern depot equipped with industrial-scale charging infrastructure, new electric buses simply cannot be deployed across the urban network. Furthermore, Ghent has concrete plans to extend its tram network, including the large-scale Gentspoort project featuring new tram links and tunnels at Dampoort and Heuvelpoort. However, in the absence of a central depot, the physical space required to stable, clean, and service the corresponding fleet is entirely lacking.

A decade of opposition and overturned permits

The backstory of the Wissenhage file reads like a chronicle of spatial planning paralysis. The plans date back more than ten years, as evidenced by the Gaardeniersbrug itself, which was built years ago with the intention of connecting to the future depot. Because the vacant land lay untouched for years, nature reclaimed it, turning it into a dense urban woodland. Local residents and campaign groups dubbed the area the Bloemekenswijkbos. Researchers and biology students from Ghent University highlighted the site's distinct ecological value as a historic wetland, quickly fuelling opposition to heavy transport infrastructure.

When the Flemish government decided to revive the project in 2021 with an earmarked budget of €170 million, public transport operator De Lijn ran into fierce institutional resistance. The then Flemish Minister for the Environment, Zuhal Demir, rejected the initial permit application in September 2022, demanding extensive revisions regarding biodiversity compensation. Although an environmental permit was eventually granted in early 2024, the conflict on the ground escalated. Environmental activists occupied the woodland, spending four months in treehouses to block scheduled felling works. De Lijn eventually began clearing the site under the supervision of bailiffs, but the legal battle shifted to the Council for Permit Disputes.

In autumn 2025, that court definitively annulled the permit. The judges ruled that De Lijn had failed to substantiate the project’s actual environmental impact adequately and had neglected to conduct a thorough evaluation of alternative locations in or around the Ghent canal zone. Consequently, the entire process had to start from scratch, while preliminary expenditure, legal fees, soil surveys, and mobility impact assessments continued to pile up on the transport operator’s balance sheet.

Although an environmental permit was eventually granted in early 2024, the conflict on the ground escalated.

The hidden operating costs of ageing diesel buses

The delays surrounding Wissenhage extend well beyond bricks, mortar, and charging bays; they directly erode De Lijn’s operating profitability. To keep timetables running in and around Ghent, the company is forced to maintain ancient diesel buses that are overdue for replacement. We note in particular how this operational inertia exerts a double drag on the operating budget: on the one hand, De Lijn faces tens of millions of euros in additional expenditure due to escalating construction costs; on the other, the routine maintenance bill for worn-out engines and exhaust systems continues to mount. These are funds that cannot be directed towards increasing frequencies or improving service quality for passengers.

Figures show that the problem is particularly acute in the province of East Flanders. Of the 408 buses operating on behalf of the transit authority there, 34.1 per cent are at least 15 years old. That figure sits significantly above the already elevated Flemish average of 28.5 per cent, with only West Flanders reporting a worse record. Ageing buses suffer far more frequent mechanical breakdowns, leading to cancelled services, delays, and frustrated commuters. While elsewhere in Flanders around 4 new electric buses from Chinese manufacturer BYD arrive each week—alongside an upcoming delivery of 94 e-buses from Daimler—these modern vehicles remain largely absent from Ghent because they have nowhere to plug in.

This creates a striking divergence within the very same province. While depots in Destelbergen, Sint-Niklaas, and Zomergem already feature the necessary charging infrastructure and are systematically scaling up capacity through 2029, the tally for electric buses and charging points in Wissenhage, Oudenaarde, Meerbeke, and Sint-Lievens-Houtem remains at zero. The so-called NIMBY effect, where neighbouring residents and local authorities oppose transformer stations and industrial chargers through formal objections, is holding back modernisation across the board.

Consequences for Flemish taxpayers and passengers

For Belgian citizens and taxpayers, the Wissenhage saga illustrates the structural vulnerability of large-scale public investment programmes in densely populated areas. The cost overrun of nearly €30 million will ultimately be funded entirely by public money. When public procurement contracts become bogged down in administrative procedures for years, the compound effect of wage indexation, pricier building materials, and tighter technical standards makes budgetary derailment inevitable.

At the same time, passengers pay a functional price for the impasse. Ghent has positioned itself as a pioneer in sustainable urban mobility through its traffic circulation plan and low-emission zone, yet public transport is currently unable to keep pace with those ambitions. As long as the central operational hub is missing, polluting Euro 5 and early Euro 6 diesel buses will continue to run through the historic city centre. This not only delays Flanders' agreed transport decarbonisation targets, but also creates a reliability crisis for commuters who rely every day on fixed bus connections to Gent-Sint-Pieters railway station or the industrial port area.

A fresh permit application with eyes on 2031

To break the deadlock, De Lijn has announced that it will submit a fully revised environmental permit application before the end of the current year. Over recent months, the operator has worked intensively to address the shortcomings identified by the Council for Permit Disputes. A comprehensive alternatives assessment has been conducted, re-evaluating several industrial locations, alongside detailed mobility and noise impact studies. In addition, the operator has requested a formal derogation under species protection regulations to provide legal cover regarding local wildlife and flora.

The schedule nevertheless remains exceptionally tight and vulnerable to further legal setbacks:

  • Permit decision: De Lijn and Minister De Ridder’s office hope to secure final approval by mid-next year, provided administrative processing proceeds without hitch.
  • Procurement and construction: Barring new injunctions, the Flemish government aims to begin actual construction works in mid-2028.
  • Commissioning: Wissenhage is not expected to be operational until 2031 to finally accommodate and charge the fleet of 120 electric buses and 40 trams.

Our assessment is that the viability of this new application rests entirely on whether De Lijn has managed to construct a watertight defence of its site selection against potential fresh appeals by local action groups. Until ground is broken, the depot in Wondelgem will remain a persistent financial and logistical headache for the Flemish mobility budget. The question is not only whether the permit will survive scrutiny mid-next year, but how many additional millions the ageing fleet will burn through in the meantime.

  • Annick De Ridder
  • begroting
  • De Lijn
  • Ghent
  • infrastructure
  • Klimaatdoelen
  • Mobility
  • Openbaar Vervoer
  • vlaanderen
  • Wissenhage
Amina El Yazidi

Written by

Amina El Yazidi

Tax Editor · Brussels (BE)

Expertise

TaxesComplianceLegislation

Amina follows tax rules around crypto in the Netherlands and Belgium. She translates fiscal legal texts into practical steps for retail investors.

Stay in the loop

Follow Block #9.

Daily market and equity news in your feed. Follow us on Facebook and Instagram so you never miss an analysis.

Also on LinkedIn

Block #9 Pro

More depth, less noise

€ 15 / month

See Pro

Practice without real money or test your knowledge?

Read more

Other interesting articles

All articles
Block Notes

By 7 a.m. you already know

Monday, Wednesday and Friday the news that matters. Sunday morning the whole week in one overview. No hype, no noise.

  • Monday, Wednesday, Friday and Sunday morning at 07:00
  • 2 min
  • No spam

Free. Unsubscribe in one click.